Site Details |
| Country: | United States |
| State: | Arizona (pop. 3665228) |
| County: | Coconino County (pop. 96591) |
| Location2: | ~10 mi S of Parks, AZ, 75 yards south of residence |
| Latitude: | 35.1406 |
| Longitude: | -111.9692 |
| Elevation: | 2046m above MSL |
| EPA Code: | 040058103 |
| Agency: | US Forest Service |
| Sponsor: | USFS |
| Region: | Mogollon Plateau |
| Land Use: | Unknown |
| AQCR: | None |
| Dates: | 9/1991 - Present |
| SiteID: | 47 |
| SiteCode: | SYCA1 |
| SiteName: | Sycamore Canyon |
| Maps: | Google, MSN, Yahoo |
Site History |
| 12/03/2002: | A1 Module Flow Calibration |
| 12/03/2002: | C1 Module Flow Calibration |
| 11/26/2001: | Sampler controller replaced |
| 11/19/2003: | A1 Module Flow Calibration |
| 11/15/2001: | Prescribed fire in the area this week |
| 09/28/2001: | Fire in the vicinity |
| 09/26/2003: | D1 Module pump replaced |
| 09/11/1991: | Ran as IMPROVE Protocol site from Sep 11 1991 12:00AM to Jul 8 1992 12:00AM |
| 09/10/2002: | Sampler controller replaced |
| 09/07/2000: | A1 Module Flow Calibration |
| 09/07/2000: | B1 Module Flow Calibration |
| 09/07/2000: | C1 Module Flow Calibration |
| 09/07/2000: | D1 Module Flow Calibration |
| 09/02/2002: | Fire in the area until 9/3/02 |
| 08/25/2001: | A1 Module Flow Calibration |
| 08/25/2001: | A1 Module pump replaced |
| 08/25/2001: | B1 Module Flow Calibration |
| 08/25/2001: | C1 Module Flow Calibration |
| 08/25/2001: | D1 Module Flow Calibration |
| 08/25/2001: | Photos taken |
| 08/25/2001: | Routine annual maintenance |
| 08/21/2002: | Fire all week smoke over IMPROVE site |
| 08/15/2002: | Fire 7 miles away |
| 08/10/2003: | lots of dust moving camp |
| 07/26/2003: | A1 Module replaced |
| 07/24/2001: | Fire around the area |
| 07/08/2004: | dust and smoke this week |
| 07/06/2001: | Fire this week |
| 07/04/2002: | lots of dust in the area |
| 07/02/2004: | dust and smoke this week |
| 06/25/2003: | Sampler controller replaced |
| 06/23/2004: | lots of dust this week |
| 06/11/2003: | Fire in area until 06/29/2003 |
| 05/27/2004: | Camp open, lots of dust in air and camp fires |
| 05/25/2001: | Summer camp started, 15 campfires |
| 05/23/2004: | A1 Module Flow Calibration |
| 05/23/2004: | B1 Module Flow Calibration |
| 05/23/2004: | C1 Module Flow Calibration |
| 05/23/2004: | D1 Module Flow Calibration |
| 05/23/2004: | Photos taken |
| 05/23/2004: | Routine annual maintenance |
| 05/22/2003: | A1 Module electronics box replaced |
| 05/20/2000: | camping activity on all Saturdays |
| 05/06/2004: | Prescribed fire in area |
| 05/01/2001: | Prescribed fire this week |
| 04/30/2004: | Prescribed fire in area |
| 04/24/2000: | Version 2 IMPROVE sampler installed |
| 04/21/2004: | A1 Module area increased from 2.20 to 3.53 sq cm |
| 04/21/2003: | A1 Module Flow Calibration |
| 04/13/2000: | A1 Module Flow Calibration |
| 04/13/2000: | B1 Module Flow Calibration |
| 04/13/2000: | C1 Module Flow Calibration |
| 04/13/2000: | D1 Module Flow Calibration |
| 04/13/2000: | Version 2 sampler installed |
| 04/08/2005: | C1 Module hose to pump relaced |
| 03/25/2004: | Fire smoke in area |
| 03/25/2003: | A1 Module Flow Calibration |
| 03/25/2003: | A1 Module pump replaced |
| 03/25/2003: | B1 Module Flow Calibration |
| 03/25/2003: | B1 Module pump replaced |
| 03/25/2003: | C1 Module Flow Calibration |
| 03/25/2003: | D1 Module Flow Calibration |
| 03/25/2003: | Photos taken |
| 03/25/2003: | Routine annual maintenance |
| 03/24/2005: | A1 Module Flow Calibration |
| 03/24/2005: | B1 Module Flow Calibration |
| 03/24/2005: | C1 Module Flow Calibration |
| 03/24/2005: | D1 Module Flow Calibration |
| 03/24/2005: | Routine annual maintenance |
| 03/24/2002: | A1 Module Flow Calibration |
| 03/24/2002: | A1 Module pump replaced |
| 03/24/2002: | B1 Module Flow Calibration |
| 03/24/2002: | B1 Module pump replaced |
| 03/24/2002: | C1 Module Flow Calibration |
| 03/24/2002: | D1 Module Flow Calibration |
| 03/24/2002: | Photos taken |
| 03/24/2002: | Routine annual maintenance |
| 03/06/2002: | Prescribed fire in forest |
| 02/27/2002: | C1 Module Flow Calibration |
| 02/20/2002: | C1 Module replaced |
| 02/08/2002: | Sampler controller replaced |
| 02/06/2002: | C1 Module electronics box replaced |
| 02/06/2002: | temperature probe replaced |
| 01/29/2003: | A1 Module electronics box replaced |
| 01/06/2004: | C1 Module pump replaced |